|
SIRTF Processing Activities
6 Mar 2003
The Space Infrared Telescope Facility (SIRTF) spacecraft arrived
at Kennedy Space Center from the Lockheed Martin plant at
Sunnyvale, Calif.
19 Mar 2003
Inspections of SIRTF’s primary mirror took place.
22 Mar 2003
The SIRTF reaction control system (RCS) was pressurized for
flight with gaseous nitrogen, which will be used to control
the spacecraft on orbit.
31 Mar 2003
Following the successful completion of functional testing,
SIRTF was mated to the Delta payload attach fitting.
5 Apr 2003
SIRTF was transported from Hangar AE to launch pad 17-B and
mated to the Boeing Delta II Heavy rocket.
18 Apr 2003
Launch is rescheduled until August to allow engineers enough
time to change out one of the nine solid rocket motors attached
to the Delta II Heavy rocket.
11 July 2003
Observatory power-on testing has
resumed and will be completed this
week.
22 July 2003
Cryogenic servicing of the observatory
with liquid helium was performed.
23 July 2003
Installation of the flight battery
is under way today.
24-25 July 2003
Closeouts of the spacecraft's electrical
system is scheduled to occur this
week. Flight batter installation
was completed on 24 July.
3 Aug 2003
Final observatory closeouts were
completed.
5 Aug 2003
Mating to the payload attach fitting
is scheduled to begin.
8 Aug 2003
Transportation to Pad 17-B is scheduled
for 10 August.
10 Aug 2003
SIRTF was rolled out of Hangar AE
early on Sunday morning, and hoisted
atop the Boeing Delta II launch
vehicle. Mechanical and electrical
connections were established, and
a spacecraft state of health check
was performed.
What processing procedures do most
spacecraft go through? Find out
in Spacecraft
Processing 101.
|